HK Electric completes first stage of emission programme

HK Electric commissioned a flue gas desulphurisation plant and a low Nitrogen Oxides System for its coal-fired generation Unit 5. It marked the completion of the first of a two-phase emission reduction programme.

The programme to retrofit emission control installations for some of the coal-fired units at the Lamma Power Station was planned four years ago with a view to meeting emission targets for 2010 set by the Government.

The installation of the FGD plant for Unit 5 will reduce more than 90 percent sulphur dioxide emission in the flue gas while the low Nitrogen Oxides burner will reduce the formation of NOx by over 60 percent.

"With the completion of the first stage of the programme, we will now move on in full force to the second stage of retrofitting two more units – with two FGD plants and one low NOx burner scheduled for completion by April next year," said HK Electric's General Manager - Projects, Dr. Tso Che-wah.

"With the completion of the entire programme, the emissions of SO2, NOx and Suspended Particulates are expected to be reduced by 11,800 tonnes, 3,300 tonnes and 114 tonnes respectively in 2010, based on the projected operation of the units. Together with our plan to increase gas-fired generation to around 30 percent, we are confident of achieving the Government’s 2010 emission targets," Dr. Tso added.

FGD plant was first installed in Lamma Power Station in the 1990s and the newly commissioned plant is the fourth to be installed and has the highest efficiency of 92 percent.

Dr. Tso is pleased that the retrofit programme has progressed as scheduled despite all the difficulties encountered. "Space and time constraints are the biggest challenges. The construction area for retrofitting Unit 5 is only 400 square meters, one-fourth of the size of our existing FGD plants. Our engineers needed to carefully plan installation procedures to fully utilise the limited space," Dr. Tso noted.

As the construction site is packed with existing facilities, HK Electric engineers had to remove existing oil tanks and relocate pipes to make space for the FGD plant. A 500-tonne crane was used to hoist main components from the surrounding area to the construction site for installation. Every step, including fire precautions, had to be precise to ensure safety.

"Time constraint was another challenge as Unit 5 is a heavy duty unit and we needed to plan the installation so as not to disrupt generation schedules," Dr. Tso said.

With the commissioning of all of the additional installations and the increased use of natural gas, it is expected that in 2010, over 95 percent of the electricity generated at the Lamma Power Station will be by gas and coal-fired units fitted with FGD and low NOx burners.

BY CESAR TORDESILLAS
Greenko readies wind projects in India
Greenko will start of its implementing its wind energy development in India.
MRC wants increased cooperation with China/Myanmar
ADB issues bonds for Asian clean energy
CPI to start constructing Kailu Jianhua project
CWP gets $734.5M loan for wind projects
HONG KONG ELECTRIC STORIES
Hong Kong’s largest solar power system gets commissioned
The largest solar power system in Hong Kong has been commissioned by HK Electric.
HK Electric to freeze 2010 tariffs
HK Electric boosts renewable energy utilization
Energy loans available to CLP, HK Electric customers
HK Electric promotes electric cooking
COMPANIES FEATURED
Hong Kong Electric
TOP NEWS
Huadian Power puts up Indonesian Branch
A subsidiary of China Huadian Corporation became the first foreign-funded company licensed to operate a power plant in Indonesia.
Three Asean countries agree on interconnected transmissions
CLP now India’s largest wind developer
ABB transformers utilised for Jilin wind substation
ABB inaugurates wind generator factory in India
PROJECT NEWS
CPI to start constructing Kailu Jianhua project
The 300MW Kailu Jianhua Wind Power Project of CPI Mengdong Energy has been ratified.
CWP gets $734.5M loan for wind projects
Huaneng to invest $880.9M in offshore wind
ADB extends $100M for India-Bangladesh interconnection
Huadian Power puts up Indonesian Branch
COMMENTS

No comments available.

Add your comment

Your Information
The content of this field is kept private and will not be shown publicly.
Your Comment
CAPTCHA
This question is for testing whether you are a human visitor and to prevent automated spam submissions.
Image CAPTCHA
Enter the characters shown in the image.