CER completes engineering design for Sinochem system

PROJECT | CER completes engineering design for Sinochem system

China Energy Recovery has completed the engineering design service for a 30MW heat recovery power generation system for Sinochem in Chongqing City.

Sinochem Fuling is a key fertilizer production subsidiary of Sinochem Corporation, a Fortune Global 500 company in China.

The detailed engineering design service is for a heat recovery retrofit project for four sulfuric acid facilities of Sinochem Fuling, with a total 1.2 million metric ton annual production capacity, one of the largest of its type in China. The retrofit project is designed to install two sets of low temperature heat recovery systems and related turbines to achieve a total 30MW power generation capacity.

Sinochem Fuling will use part of the recovered heat energy to generate electricity to sell to the power grid and utilize the remaining in the form of steam directly in its production process.

This design service contract was entered into in September 2008 which was announced then too.

CHINA ENERGY RECOVERY STORIES

$10M loan raised for new CER facility
China Energy Recovery's new Shanghai production facility will get a $5 million funding for development and construction.
CER completes $1.42M contract for Yangfeng
CER Sept contracts up $10M with $5M Sanning deal
CER wins Wuxi Zhenyu waste heat recovery deal
CER gets financing deal for manufacturing plant

BY CESAR TORDESILLAS

Wujing co-generation starts commercial operations
Wujing co-generation modification project's Unit 8 passed 168-hour test running simultaneous with the desulphurisation and de-Nox systems.
Xinchang plant's Unit 2 passes run test
Areva awarded Indian Extra High Voltage projects
CPI’s carbon capture facility officially commissioned
$10M loan raised for new CER facility

COMPANIES FEATURED

China Energy Recovery